Speed-to-Power for National Data Center Developer

The Challenge

Builder and operator of dozens of data center campuses needed assistance with utility interconnection and infrastructure for a data center being built and marketed to prospective buyers.

Solution

Priority Power managed significant land work on the property, engineering and designing a 50 MW substation with two transformers and the option for a third to accommodate growth. The project was completed 9 months ahead of schedule. 

Services

  • Energy Procurement
  • Asset Management
  • Energy Infrastructure

Bottom Line

Engaging PPM at the outset of the project saw completion well ahead of schedule.