Contact Us

BTC Miner Leverages Historic ERCOT Procurement Contract

The Challenge

Hyperscale data center operator lacked in-house expertise to maximize energy cost efficiencies while scaling for future growth.

Solution

Priority Power negotiated one of the largest procurement contracts in ERCOT history, securing load for the next ten years. Load management was handed by PPM’s 24/7 NOC, and a new substation and distribution infrastructure were delivered to expand interconnection capacity.

Services

  • Energy Procurement
  • Asset Management
  • Energy Infrastructure
  • Market Intelligence & Data Advisory

Bottom Line

Long-term power secured at ~50% below market rate, with additional Load Management savings.